HV cabine
DCO² is connected to 2HV feeds of 11kV. This gives DCO² the possibility to separate the power feed up to the HV feed.
In total, the datacenter has 5MW power feeds (good for 4.5MW IT power)
The build out of the power infrastructure will be done in 500kVA steps. In this way we can anticipate on the different needs of customers in a colocation environment without the burden of overcapacity.